In November, we reported that Holland BPW had a goal of 126 customers by the end of 2018, with 79 already signed up. Let’s see where we are today now that the new network is coming online.
Customers who sign up now (and 6 already on the list) will be part of a “phase 2” build, which will take place late spring or early summer.
BPW has done zero promotion of the project since November, as they focus on built-out. We expect to see a new push once they identify a wider area that can also be in “phase 2.”
Customer hookups have taken longer than planned. We expect demand to increase once more people experience gigabit fiber.
Have questions? Want to help? Email us: info@hollandfiber.org and talk about #HollandFiber.
Website built in Holland, Michigan by
“customers who sign up now” – HOW? No signup link!
You used to have a page where someone could put in their address to express interest, so that you could track where to expand? - where did it go?
Hopefully you can address both of these in a subsequent update.
Yes, BPW’s sign up page is here: https://fiber.hollandbpw.com/pages/service-area/
Even if you’re not in the current area, it helps them gauge demand and pick where to go next.
I’ve also updated the link in the post. Thanks!